Chemical and Biopharmaceutical Cleanroom Construction

Chemical and biopharmaceutical cleanroom — ceiling first, conditions by zone — concept diagram

Layout and the floor track come first; the walkable ceiling is hung next, and the wall panels are set in the track and fastened to the ceiling. Doors, flush windows and pass-throughs go in; above-ceiling MEP and the terminal HEPA housings are installed from the walkable deck, with an air shower where specified.

Bio utilities come from the interstitial space through sealed ceiling penetrations and a wall chase to a flush utility panel. Rooms are labeled ISO 8, ISO 7 and CNC (ISO 5 only as a local zone); pressure is shown as relative symbols only. In the chemical zone, local exhaust is captured at chemical handling points.

In this film

  1. 01Zones in section
  2. 02Layout and floor track
  3. 03Walkable ceiling first
  4. 04Wall panels fastened to the ceiling
  5. 05Doors, flush windows and pass-throughs
  6. 06Air shower (where specified)
  7. 07Above-ceiling MEP
  8. 08HEPA terminals and low-wall returns
  9. 09Finishes and integral cove
  10. 10Equipment setting and hook-up
  11. 11Utility routing
  12. 12Security and server room
  13. 13Joints and penetrations sealed
  14. 14Pressure and flow
  15. 15Turnover support

Typical sequence — varies by system and project.

Illustrative zoning. Room classifications, pressures and layouts are project-specific and determined by each owner's risk assessment.

Cleanliness, airflow, room pressurization and hazardous-location classification are determined per project design, the owner's area classification and applicable codes.