Concept video · 1 min 16 s
Semiconductor Cleanroom Construction: System Ceiling and Overhead AMHS

The access floor is leveled first to a finished floor datum taken from the project benchmark, then protected. Anchor bolts go into the concrete structure above, threaded rods and turnbuckles hang the ceiling grid, and the grid is leveled to the floor datum. FFUs seat in gel seal on a knife edge, with filter faces coplanar with the grid.
After the FFUs, AMHS rails hang from the grid main tees. Tools are moved in and set on the leveled floor. Tool power runs from sub-fab panelboards through a sealed slab penetration and under the access floor to each tool's main disconnect, and process hook-up comes from below too. PROCON coordinates and installs the FFUs, the ceiling grid and the AMHS rails as one package.
In this film
- 01Access floor and levelingBenchmark → finished floor datum, pedestal leveling, stringers and perforated panels, floor protection
- 02Structure above and anchor boltsDrill → anchor bolt → nut and washer
- 03Threaded rods and ceiling gridThreaded rods and turnbuckles, main tees, cross tees and connectors
- 04Grid levelingThe floor datum carried up to the grid
- 05Gel seal and FFUsGel seal and knife edge: FFU filter faces coplanar with the grid, blind panels and lights
- 06Air showerGowning room → air shower → fab, interlocked doors
- 07AMHS railsRails hung from the grid main tees after the FFUs
- 08Equipment setting and installationTool move-in and setting
- 09Underfloor power distribution and equipment connectionsSub-fab panelboards → sealed penetration → feeder → tool main disconnect; process hook-up from below too
- 10Controls · communicationsTool control wiring, fiber backbone
- 11OHT transportFOUP to the load port
- 12Turnover supportPROCON supports the turnover
Typical sequence — varies by system and project.
Illustrative only. Not to scale. Details, sequences and dimensions vary by project.
More videos
1 min 37 sChemical and Biopharmaceutical Cleanroom ConstructionHow PROCON E&C builds a chemical and biopharmaceutical cleanroom: layout and the floor track, the walkable ceiling first, wall panels fastened to the ceiling, doors, flush windows and pass-throughs, above-ceiling MEP and terminal HEPA housings, utilities from the interstitial space, sealing, and turnover support.
1 min 25 sIntegrated Electrical, Controls and Low-Voltage SystemsHow one PROCON E&C team delivers integrated electrical, controls and low-voltage systems: BIM coordination, power distribution, equipment setting and hook-up, utilities and backup power, instrumentation and controls, network infrastructure, electronic security, server and IT rooms, facility electrical, and testing and turnover.
1 min 48 sPlanned Lift: Lift and Rigging Plans Prepared In-HouseHow PROCON E&C plans a lift before the crane arrives: crane position, outriggers and crane mats, working radius and the load chart check, the rigging plan and pick sequence, choosing the lift method, pre-lift checks, then a motorized skylight and rooftop units set on the roof.